[GUEST ACCESS MODE: Data is scrambled or limited to provide examples. Make requests using your API key to unlock full data. Check https://lunarcrush.ai/auth for authentication information.]  MS Ingawa [@MSIngawa](/creator/twitter/MSIngawa) on x 113.3K followers Created: 2025-07-16 14:47:16 UTC Buhari Legacy 11: Apapa–Oshodi–Oworonshoki Road It’s a major XX km arterial highway linking Apapa Port (which includes Tin Can Island and Apapa Wharf) to inland Lagos via Oshodi, Oworonshoki, and Ojota . Originally built in the mid-1970s, it’s the primary evacuation route for port cargo and traffic from Lagos airport and the Trans‑West Africa Highway In November 2018, President Buhari flagged off the reconstruction under a tax-credit PPP involving Dangote Industries and subcontractor Hitech Construction. Construction began in early 2019, with an expected two‑year delivery. By April 2021, the expressway was declared “virtually ready” President Tinubu officially inaugurated the fully reconstructed expressway in May 2024, marking a significant upgrade to port access. This is a vital infrastructure to the national economy and also a major legacy for Buhari.  XXXXXX engagements  [Post Link](https://x.com/MSIngawa/status/1945495453623283917)
[GUEST ACCESS MODE: Data is scrambled or limited to provide examples. Make requests using your API key to unlock full data. Check https://lunarcrush.ai/auth for authentication information.]
MS Ingawa @MSIngawa on x 113.3K followers
Created: 2025-07-16 14:47:16 UTC
Buhari Legacy 11: Apapa–Oshodi–Oworonshoki Road
It’s a major XX km arterial highway linking Apapa Port (which includes Tin Can Island and Apapa Wharf) to inland Lagos via Oshodi, Oworonshoki, and Ojota . Originally built in the mid-1970s, it’s the primary evacuation route for port cargo and traffic from Lagos airport and the Trans‑West Africa Highway
In November 2018, President Buhari flagged off the reconstruction under a tax-credit PPP involving Dangote Industries and subcontractor Hitech Construction. Construction began in early 2019, with an expected two‑year delivery. By April 2021, the expressway was declared “virtually ready”
President Tinubu officially inaugurated the fully reconstructed expressway in May 2024, marking a significant upgrade to port access.
This is a vital infrastructure to the national economy and also a major legacy for Buhari.